DIRECT EXHAUST — Sidewall
Determine termination location
1. e vent termination must be installed as shown in Figure32 and
in Figure34, page38.
2. e termination placement must comply with clearances and
limitations shown in Figure31, page36.
3. Locate the termination so is not likely to be damaged by foreign
objects, such as stones or balls, or subject to buildup of leaves or
sediment.
4. Install the boiler in a location that allows proper routing of all vent
piping from the boiler vent connection to the selected sidewall
location.
Multiple vent terminations
1. When terminating multiple SlimFit boilers, terminate each vent
connection as described in this manual. See Figure33,page38
for typical layout.
2. Place wall penetrations to obtain minimum clearances shown in
Figure32 for U. S. installations.
3. For Canadian installations, provide clearances required by CAN/
CSA B149.1 Installation Code and a ULCS636 compliant vent kit.
Install vent piping
See 7!2.).' about boiler vent/air outlet seals and
clamp on page29. Verify that the seal is installed cor-
rectly before inserting the vent manufacturer’s SlimFit
Vent Adapter.
USE SWEEP ELBOWS FOR ALL VENT PIPING
WHEN POSSIBLE — Short-radius elbows cause
higher pressure loss, resulting in less allowable
vent/air piping length. See Figure 27, page 30
for maximum lengths and reductions required
for fittings.
1. Install the vent manufacturer’s SlimFit Vent Adapter in the boiler
vent outlet. Follow all vent manufacturer instructions.
2. Install a vent manufacturer reducer if needed to adapt to the vent
size being used.
3. Slope vent piping toward the boiler slope vent piping a mini-
mum of ¼inch per foot in horizontal runs or larger per vent pipe
manufacturer’s instructions.
4. Support piping independently of the boiler Install pipe sup-
ports every 5feet on both the horizontal and vertical runs. Install
a hanger support within 6inches of any upturn in the piping. Or
follow vent pipe manufacturer’s instructions.
Install vent termination elbow
1. Maintain the required dimensions of the nished termination
piping as shown in Figure32,page37.
&IGURE Sidewall direct exhaust termination
5SE ONLYTHE VENT MATERIALS AND KITS
listed in &IGUREPAGE
.
Read and follow all instructions in this
manual.
$/./4PROCEEDWITHVENTIN-
STALLATIONUNTILYOUHAVEREADPAGE
through page 36.
Locate the termination such that the total
vent piping from the boiler to the termi-
nation WILL NOT EXCEED THE MAXIMUM
LENGTHGIVENIN&IGUREPAGE
.
#OMPLYWITHALLVENTSYSTEMMANUFAC-
turer’s instructions.
Provide a vent manufacturer’s SlimFit Vent
Adapter and reducer (if needed) at the boiler
vent connection.
Every joint on
POLYPROPYLENEVENTPIP-
ing
MUST include a locking collar. Failure to
supply locking collars could result in vent/
air piping leakage.